ANALISIS PERCEPATAN WAKTU TERHADAP BIAYA DENGAN METODE TIME COST TRADE OFF (Studi Kasus Proyek Pembangunan Gedung Islamic Center Kec. Rimbo Bujang Kab. Tebo Provinsi Jambi)
Abstract
Cost and time are critical factors in construction projects. Therefore, it is essential to determine the optimal cost and time by performing Crashing on activities within the critical path. The analysis begins by identifying the critical path using the Critical Path Method (CPM), followed by crashing the activities on the critical path. In this study, acceleration is achieved through three alternatives: adding 2 hours of overtime (alternative 1), increasing the workforce (alternative 2), and adding a night shift (alternative 3). The determination of the optimal cost and time is based on two key variablel cost and time utilizing Euclidean, analysis to identify the most efficient trade-off between the two.. The analysis reveals that the most optimal alternative is alternative 2 (increasing the workforce). The project's normal completion time is 210 calendar days with a cost of IDR 4,483,505,000 By applying Crashing, the project completion time is reduced to 148 calendar days, resulting in a time saving of 62 calendar days. However, this acceleration increases the cost to IDR 4,583,211,000 an additional IDR 99,705,000 Thus, alternative 2 is considered optimal compared to alternatives 1 and 3 in terms of cost and time.
References
Anggraeni, D. N., Nugroho, M. W., & Sumarsono. (2019b). Optimasi Waktu dan Biaya Crashing dengan Menggunakan Metode Time Cost Trade Off. 4(2), 310–317.
Ghassani, D. B., Albab, U., Sipil, T., & Selamat Sri, U. (2023). Perencanaan Waktu Dan Biaya Menggunakan Metode Crashing Dengan Sistem Kerja Shift (Studi Kasus : Proyek Pembangunan Puskesmas Sukorejo II). JERA : Journal Engineering Research and Application, 2(1), 7–13.
Hakim, A. L., Yulianto, T., & Nugroho, M. W. (2023). Optimalisasi Waktu dan Biaya Menggunakan Metode Crashing Program pada Proyek Gedung BPJS Tulungagung. Briliant: Jurnal Riset dan Konseptual, 8(1), 241.
Indra, I. F., Rita, E., & Rahmat. (2020a). Analisa Percepatan Waktu Pelaksanaan Proyek Dengan Metode Time Cost Trade Off (Tcto). Student Journal …, 57–58.
Indra, I. F., Rita, E., & Rahmat. (2020b). Analisa Percepatan Waktu Pelaksanaan Proyek Dengan Metode Time Cost Trade Off (Tcto). Student Journal …, 57–58.
Musa, R. S., Kusuma, J., & Ilyas, N. (2020). Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan Kelas Darurat. 1–10.
Purnomo, A., Nugroho, M. W., & Yulianto, T. (2019). Pengendalian Biaya dan Waktu Proyek Gedung SMK Dwija Bhakti Jombang Dengan Menggunakan Metode Earned Value. 4(5), 40–52.
Ramadhan, P. M., & Anwar, S. (2022). Jurnal Konstruksi Dan Infrastruktur Teknik Sipil Dan Perencanaan Analisis Manajemen Konstruksi Pada Jembatan Cikeusal. Jurnal Konstruksi dan Infrastruktur UGJ CIREBON Jurnal Konstruksi dan Infrastruktur, X(1), 1–6.
Salakory, N. C., Jamlaay, O., & Titaley, H. D. (2023). Analisa Percepatan Waktu Pada Proyek Pembangunan Struktur Gedung Laboratorium Unpatti Mengunakan Metode Crashing Program Dan Fast-Track. 2(1), 29–39.
Sutrisno, Audi, Pramudya, R. E. Listyanto. (2023). Implementasi Metode CPM , Crashing dan PERT Pada Penjadwalan Proyek Pembangunan Masjid dan Asrama Yatim Piatu Barokah Amanah Mustaqbal. jurnal serambi engineering, VIII(2), 5390–5400.
Tama, A. K., Anggraini, L., & Tutuko, B. (2020). Analisis Kinerja Manajemen Konstruksi Pada Proyek Gedung Digitasi Universitas Negeri Semarang. Teknik Sipil, 1–15.
Yuneta, M., Kurniaty, M., & Kabupung, A. S. (2024). Analisis Pengendalian Waktu Dan Biaya Menggunakan Critical Path Method ( Cpm ) Dengan Aplikasi Microsoft Project 2016. 12–19.

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.










2.png)
.png)





.png)