ANALISIS PERBANDINGAN BIAYA DAN WAKTU PELAKSANAAN BETON HALF SLAB DENGAN BETON KONVENSIONAL PADA PROYEK REVITALISASI MUSEUM MANDALA MATHIKA SUBAK
Abstract
The construction implementation system in the Mandala Mathika Subak Museum Revitalization project uses the cast in situ or conventional method including floor slab work. The implementation of floor slab work with the cast in situ method requires a long processing time and a lot of labor and costs incurred. In the construction of the building, the selection of work methods is very influential on the implementation time and cost. The selection of the right method will make the development efficient. One of them is the use of precast concrete such as half slab. In this study will compare conventional methods and half slab methods from the aspects of implementation time and cost, which is more profitable. The results of the comparative analysis of execution time and costs from the calculation of cast-in-situ and half-slab plates in the Revitalization Project of the Mandala Mathika Subak Museum show that using the half-slab method saves 33% in costs compared to the cast-in-situ method, with a cost difference of Rp. 552,730,037, and can accelerate the execution time of 43% or 19 days.
References
Arumsari, P., & Palagian, B. (2024). Comparison of Conventional and Precast Half Slab Work Methods (Case Study: Japfa Office Building Daan - Mogot). IOP Conference Series: Earth and Environmental Science, 1324(1). https://doi.org/10.1088/1755-1315/1324/1/012012
Cho, K., Shin, Y. su, & Kim, T. (2017). Effects of Half-Precast Concrete Slab System on Construction Productivity. Sustainability (Switzerland), 9(7). https://doi.org/10.3390/su9071268
Diputera, I. G. A., & Kurniari, K. (2020). Analisis Perbandingan Biaya Pekerjaan Pelat Lantai Menggunakan Pelat Konvensional dan Pelat Bondek pada Proyek Apartemen Taman Sari. Fakultas Teknik UNR, 40–49. http://www.ojs.unr.ac.id/index.php/teknikgradien/article/download/461/424/
Hendarti, L. (2021). Analisis Perbandingan Biaya Pelaksanaan Pelat Beton dengan Metode Bondex dan Konvensional. Surakarta Civil Engineering Review, 25–32.
Hidayah, R., Ridwan, A., & Cahyo, Y. (2018). Analisa Perbandingan Manajemen Waktu Antara Perencanaan Dan Pelaksanaan (Studi Kasus: Pada Gedung Asrama Pondok Pesantren Sananul Huda Di Selorejo Kab. Blitar). Jurnal Manajemen Teknologi & Teknik Sipil, 1(2), 281–290. https://doi.org/10.30737/jurmateks.v1i2.416
Holla, B. R. K., Anant, S., Mohammad, M. A., Periwal, A., & Kapoor, A. (2008). Time, Cost , Productivity and Quality Analysis of Precast Concrete System. International Journal of Innovative Science, Engineering & Technology, 3(5), 252–257. www.ijiset.com
Juansyah, Y., Oktarina, D., & Zulfiqar, M. (2017). Analisis Perbandingan Rencana Anggaran Biaya Bangunan Menggunakan Metode SNI dan BOW. Jurnal Rekayasa, Teknologi, Dan Sains, 1(1), 1–3.
Kristiana, R., Sinulingga, J. F., Sediyanto, S., & Wedhasari, T. (2022). Komparasi Efektivitas Waktu dan Efisiensi Biaya Antara Metode Konvensional Dan Half Slab Pada Struktur Pelat. IKRAITH-Teknologi, 6(3), 103–108. https://doi.org/10.37817/ikraith-teknologi.v6i3.2311
Najoan, C. H., Tjakra, J., & Pratasis, P. A. K. (2016). Analisis metode pelaksanaan plat precast dengan plat konvensional ditinjau dari waktu dan biaya (Studi Kasus Markas Komando Daerah Militer Manado). Jurnal Sipil Statik, 4(2016), 319–327. https://ejournal.unsrat.ac.id/index.php/jss/article/view/12552/12124
Romadhoni, M., & Muh. Nur Sahid. (2023). Efektivitas Metode Pekerjaan Pelat Lantai Bondek, Half Precast dan Konvensional Gedung Asrama Putra Al-Azhar. Jurnal Manajemen Teknologi & Teknik Sipil, 6(2), 99–111. https://doi.org/10.30737/jurmateks.v6i2.4949
Wisanggeni, D. H. (2017). Perbandingan Sistem Pelat Konvensional dan Precast Half Slab Ditinjau Dari Segi Waktu dan Biaya Pada Proyek My Tower Apartement Surabaya. Institut Teknologi Sepuluh Nopember, 1–219.

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.










2.png)
.png)





.png)